Enterprise Internet Gateway Solution


Project Description:


Leadership

Division:
Networking
Division Officer:
Charles Walker
Dept President:
Troy Bounty
Dept Manager:
Yoshida Daiki
Department Sr. V.P.:
Charles Walker
Department VP:
Robert Brown

Project Team

Sponsor:
Nicholas Cook
Program Manager:
Project Manager:
Russell Graham

Project Stats

Status:
status (Y)
Project Phase:
Implementation
Phase % Complete:
35%
Project % Comp:
75%
Risks:
0
Issues:
0

Delivery Dates

Sched. Start:
02-12-2024
Sched. End:
07-25-2024
Actual Start:
02-12-2024
Actual End:
08-15-2024
Variance:
14 Days (-26%)

Finances

Approved Budget:
$1,258,987
Change Costs:
$0
Revised Budgets:
$1,258,987
CRs:
Project Actuals:
$802,604
Earned Value:
0.01

Resources

Architect:
Yamada Aoi
Engineer:
Enrique Rios
Developer:
George Scott
Network:
Pedro Antonio
Database:
Karen Scott

Issue Notes