California Intrusion Reporting


Project Description:


Leadership

Division:
Marketing
Division Officer:
Manuel Diaz
Dept President:
Ai Kwon
Dept Manager:
Yamada Aoi
Department Sr. V.P.:
Manuel Diaz
Department VP:
Linda Davis

Project Team

Sponsor:
Jessica Morgan
Program Manager:
Evelyn Woods
Project Manager:
Evelyn Woods

Project Stats

Status:
status (C)
Project Phase:
Maintenance
Phase % Complete:
45%
Project % Comp:
35%
Risks:
0
Issues:
0

Delivery Dates

Sched. Start:
03-04-2024
Sched. End:
07-25-2024
Actual Start:
03-04-2024
Actual End:
08-31-2024
Variance:
14 Days (-10%)

Finances

Approved Budget:
$132,006
Change Costs:
$0
Revised Budgets:
$132,006
CRs:
Project Actuals:
$39,734
Earned Value:
0.01

Resources

Architect:
Stephanie Rivera
Engineer:
Joseph Clark
Developer:
Luis Fernando
Network:
Susan Taylor
Database:
Edward Green

Issue Notes