NT Server Removal
Project Description:
Leadership
Division:
Security
Division Officer:
Mark Hall
Dept President:
Antonio Lopez
Dept Manager:
Kimura Shota
Department Sr. V.P.:
Mark Hall
Department VP:
Richard Anderso
Project Stats
Status:
Project Phase:
Testing
Phase % Complete:
35%
Project % Comp:
85%
Risks:
Issues:
Action Items:
Decisions:
Finances
Approved Budget:
$2,500,000
Change Costs:
$86,300
Revised Budgets:
$2,586,300
CRs:
Project Actuals:
$2,572,075
Earned Value:
0.01
Project Team
Sponsor:
Larry Cooper
Program Manager:
Project Manager:
Juan Cole
Delivery Dates
Sched. Start:
04-15-2024
Sched. End:
09-15-2024
Actual Start:
04-15-2024
Actual End:
09-29-2024
Variance:
21 Days (-13%)
Resources
Architect:
Brandon Ward
Engineer:
Antonio Gome
Developer:
Donald Baker
Network:
Charles Jackson
Database:
Alexey Lebedev