Project Mgmt Methodology and SDLC


Project Description:


Leadership

Division:
HR
Division Officer:
Paul Young
Dept President:
Olivia White
Dept Manager:
Hayashi Mio
Department Sr. V.P.:
Paul Young
Department VP:
Charles Jackson

Project Team

Sponsor:
Scott Cox
Program Manager:
Project Manager:
Fred Jordan

Project Stats

Status:
status (G)
Project Phase:
Requirements
Phase % Complete:
65%
Project % Comp:
50%
Risks:
0
Issues:
0

Delivery Dates

Sched. Start:
04-15-2024
Sched. End:
06-24-2024
Actual Start:
04-15-2024
Actual End:
06-24-2024
Variance:
14 Days (-11%)

Finances

Approved Budget:
$45,773
Change Costs:
$0
Revised Budgets:
$45,773
CRs:
Project Actuals:
$23,573
Earned Value:
0.01

Resources

Architect:
Justin Peterson
Engineer:
Diego Fernan
Developer:
Carlos Eduardo
Network:
Francisco Jose
Database:
Kato Rina

Issue Notes