Sharkwire Integration
Project Description:
Leadership
Division:
Finance
Division Officer:
Kevin King
Dept President:
JamesMadison
Dept Manager:
Mori Yuto
Department Sr. V.P.:
Kevin King
Department VP:
Sarah White
Project Stats
Status:
Project Phase:
Design
Phase % Complete:
45%
Project % Comp:
60%
Risks:
Issues:
Action Items:
Decisions:
Finances
Approved Budget:
$56,209
Change Costs:
$0
Revised Budgets:
$56,209
CRs:
Project Actuals:
$40,133
Earned Value:
0.01
Project Team
Sponsor:
Laura Howard
Program Manager:
Project Manager:
Virginia Perry
Delivery Dates
Sched. Start:
04-15-2024
Sched. End:
08-25-2024
Actual Start:
04-15-2024
Actual End:
09-08-2024
Variance:
0 Days (0%)
Resources
Architect:
Angela Gray
Engineer:
Rafael Moral
Developer:
Ronald Nelson
Network:
Sarah White
Database:
Laurent Moreau