| ID | Risk Title | Risk Description | Probability | Severity | Date Opened Date Closed |
Status | Owner |
|---|---|---|---|---|---|---|---|
| 2 | Christmas freeze may impact deployments deemed need for testing | There is a significant risk that the annual "Christmas Freeze" on production deployments—tentatively schedule for December 15th through January 3rd — will delay the critical path of the project, resulting in a minimum three-week slippage of the Go-Live date and potential budget overruns due to extended resource retention. | 3 | 3 | 11-20-2024 N/A |
Open | Chris Freeman |